Lehigh Acres Middle School Concession & ADA Access

Start Date:

6/27/2018


Status: Completed
For Department: Parks & Recreation

Details: Renovations and ADA improvements to the concession stand located at the soccer fields at Lehigh Acres Middle School to include a new sidewalk, ramp, and three parking spaces that will all be ADA compliant.
The project is currently in the design phase which began on 05/01/2017 and the anticipated start of construction is 06/27/2018.
Estimated Completion Date: 10/19/2018

Location: Lehigh Middle School 104 Arthur Avenue, Lehigh Acres, FL 33936[ MAP ]

Cost: $217,290
Funding Source: General Fund
Project Manager: Richard P. Whalen, P.E. Phone: 239-281-5258 Email: RWhalen@leegov.com

Contractor:Owen-Ames-Kimball Company
Engineer: Bean, Whitaker, Lutz & Kareh, Inc. (BWL&K)
Architect: FC&M Staff and BWL&K