Status: Completed
For Department: Parks & Recreation
Details: Renovations and ADA improvements to the concession stand located at the soccer fields at Lehigh Acres Middle School to include a new sidewalk, ramp, and three parking spaces that will all be ADA compliant.
The project is currently in the design phase which began on 05/01/2017 and the anticipated start of construction is 06/27/2018.
Estimated Completion Date: 10/19/2018
Location: Lehigh Middle School 104 Arthur Avenue, Lehigh Acres, FL 33936[
MAP ]
Cost: $217,290
Funding Source: General Fund
Project Manager: Richard P. Whalen, P.E.
Phone: 239-281-5258
Email: RWhalen@leegov.com
Contractor:Owen-Ames-Kimball Company
Engineer: Bean, Whitaker, Lutz & Kareh, Inc. (BWL&K)
Architect: FC&M Staff and BWL&K