Task 1: Project Coordination (11/18 - 5/20)

Task 2: Identification of Potential Flood Improvement Projects (11/18 - 3/19)

Task 3: Regional Model Development (11/18 - 11/19)

Task 4: Modeling of Flood Mitigation Projects (9/19 - 4/20)

Task 5: Surveying (2/19 - 6/19)

Task 6: Agency Coordination (5/20)

Task 7: Project 1.1 - East Lee Coounty (12/19 - 4/20)

Task 7: Project 1.2 - Whiskey Creek (12/19 - 4/20)

Task 7: Project 1.3 - Southeast Lee County (12/19 - 4/20)

Task 7: Project 1.4 - South Fort Myers (12/19 - 4/20)

Task 8: Priority Matrix (1/20 - 4/20)

Task 9: Public Involvement (11/18 - 5/20)

Task 10: Build Out Analysis (2/20 - 3/20)

Task 11: Basin Storage/Discharge Analysis (3/20 - 4/20)

Task 12: Summary Report (4/20 - 5/20)

Schedule